The Milestones of the Export of Iron Ore
Looking back through time
Saldanha Bay, located on the western seaboard of South Africa has long been known to be the best natural harbour on the African coast, a fact which remained hidden for centuries until 1601, when it was stumbled upon by Dutch explorer Van Spilbergen.
Its potential as a deep sea port lay dormant until 1969 when feasibility studies for an extensive iron ore export project recognised Saldanha Bay as the perfect setting for a port that would launch South African Iron Ore into the world market.
Construction of the 861 kilometre line began a few years later on the 1st of June 1973 and drew to completion with the arrival of the first iron ore train in Saldanha Bay on 14 May 1976.
Over time, the operation has continued to break new ground in positioning Transnet Freight Rail as a leader in the South African business community and indeed as an icon in the heavy haul and rail transportation industries, locally and abroad.
1 June 1973
Construction begins
14 May 1976
First iron-ore from Sishen arrives at Saldanha.
27 September 1976
First export consignment leaves Saldanha on the “Fern Sea”
April 1978
Sishen-Saldanha line taken over by South African Railways & Harbours
15 November 1978
First train with Beeshoek (near Postmasburg) Ore arrives at Saldanha
1979/80
More than 18 million tons of Iron Ore is exported in a single year
January 1980
First metal concentrate from Aggeneys arrives at Saldanha
30 October 1984
The 100 millionth ton of Iron Ore is exported
July 1988
The largest single consignment ever of Export Iron Ore (293 280 t) is loaded
26 August 1989
A once-off record-breaking “Monster Train” of over 7km in length is listed in the Guinness Book of Records
1992
Total Iron Ore exported since start-up reaches 200 million ton level
1994/95
More than 20 million tons is exported in a single financial year
1995/96
22 259 million tons of Iron Ore exported in a single financial year
20 February 1998
Amalgamated ISO listing is awarded
1998
Total Iron Ore exported since start-up reaches 300 million ton level
September 1999
Gold Award from the National Productivity Institute (NPI) to business partners Transnet Freight Rail, Transnet Port Terminals port of Saldanha and Iscor for outstanding achievement in productivity improvement (M-ORE Project.)
2001
The Iron Ore Export Channel celebrates its 25th anniversary
2001
Total Iron Ore exported since start-up reaches 400 million ton level
October 2002
Winner of the Annual Logistics Achiever Awards for the M-ORE (capacity expansion) project
22 February 2004
The highest tonnage throughput for one week is recorded at 585 012 tons
August 2004
Radio Distributed Power: Proof of concept tests and radio receptivity tests by means of voice controlled Distributed Power train
2005
Total Iron Ore exported since start-up reaches 500 million ton level
August 2005
Voice controlled DP test train in both directions, introducing different train compilation to 2004 test
August 2005
Voice controlled DP test train in both directions, introducing different train compilation to 2004 test
August 2006
Locotrol RDP equipment tested on train consist of 5x 9E and 3x DE and a single train driver
August 2007
RDP test train to verify parameters, witnessed by Railway Safety Regulator
August 2007
RDP test train to verify parameters, witnessed by Railway Safety Regulator
17 December 2007
First ever 342 RDP production train departs from Sishen
May 2008
New Iron Ore mine at Khumani starts railing Iron Ore for export markets
2008
Total Iron Ore exported since start-up reaches 600 million ton level
5 July 2009
New weekly throughput record of 899,592 tons in a single week
6 July 2009
1000th loaded RDP train arrives at Saldanha
26 July 2009
Highest ever weekly throughput of 955,800 tons in a single week. First time ever that actual production matches planned production 100% normally line operates at 95% efficiency
10 August 2009
One billionth gross ton (mass of locomotives + mass of wagon s + mass of iron ore) traverses the iron ore line
15 September 2009
The first new generation 15E class locomotive, locomotive number 15001 is delivered to the Export Iron Ore Line
28 September 2011
A total of 44 new generation 15E class locomotives have already been commissioned on the Export Iron Ore Line…paving the way for the capacity expansion on the line
20 November 2012
The first train with Iron Ore from the Kolomela Mine departs
26 March 2012
The Export Iron Ore Line ended the 2011/2012 financial year on a high by setting a new operations weekly throughput record of 1,222,000 million tons
Why book with us?
We offer superior 4 star accredited self catering & bed and breakfast accommodation in Vredendal & Lutzville. We are a fully compliant
B-BBEEE business.
Follow Us
Quick Links
Mail Us @
info@melkboomsdrift.co.za
Call Us
t: +27 (0) 27 217 2624
m: +27 (0) 82 900 1383
Find Us
GPS: 31°36'14.41"S | 18°24'20.01"E